Update construction progress of Myanmar Meranti project’s Ruby in July 2018
By the end of July 2018, construction for the whole foundation of the main workshop of the Myanmar Meranti project’s Ruby has been completed by INVESTCORP Myanmar.
At present, ground levelling, foundation concrete and ground concrete are being constructed by INVESTCORP Myanmar. It is expected that in August 2018, 50% of the ground square of the workshop will be finished.
The auxiliary items such as pits inside the workshop, ancillary houses and waste water treatment tank will be carried out in the coming time.




Other news
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED