Update construction progress of Myanmar Meranti project’s Ruby in May 2018
By the end of May 2018, the Myanmar Meranti project’s Ruby has been completed all the foundation work for the production building by INVESTCORP Myanmar.
At the present time, 60% of the bracing beam has been done and as expected, all of this work will be completed on June 20, 2018.
For the floor of the production building area, INVESTCORP Myanmar is carying out cutting floor piles.
Other news
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED