Update construction progress of Myanmar Meranti project’s Ruby in May 2019

In May 2019, INVESTCORP Myanmar continued to execute the painting and finishing works of the ancillary area. Other finishing works are also implemented in parallel.

The additional PIT foundation inside the factory has been completed and handed over to the Owner for use. At present, INVESTCORP Myanmar is doing cleaning work and gluing expansion joints.

At the main workshop area, INVESTCORP Myanmar is carrying out the painting work and completing 90% of the workload. Finishing work of the toilet area is continuing to be executed and be expected to complete on June 15, 2019. Besides, some other finishing works are also being implemented.