Update construction progress of Myanmar Meranti project’s Ruby in Sep 2018
In Sep 2018, at the Myanmar Meranti project’s Ruby, 60% of the production building’s ground area has been done by INVESTCORP Myanmar. The remaining area will be continued to implement after the foundation for machines is completed.
At the moment, INVESTCORP Myanmar is constructing the enclosing wall around the factory and cable trough for the power room.
It is expected in Oct 2018, construction of foundation for machines inside the production building and some auxiliary items will be carried out by INVESTCORP Myanmar.


Other news
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED