Update construction progress of New pressing factory project of Mitsuba M-Tech Co. Ltd in June 2018
In June 2018, at the New pressing factory project of Mitsuba M-Tech Co. Ltd, excavation work has been started proceeding. Besides, foundation and bracing beam are also constructed in parallel. As expectation, all of the foundation and bracing beam will have been finished by the end of July 2018.
As soon as the concrete work for foundation and bracing beam are finished, the reinforcement and formwork will be carried out by INVESTCORP. At present, piling work for the whole project is being implemented.

Other news
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED