On Nov 15, 2018, the New pressing factory project of Mitsuba M-Tech Vietnam Co. Ltd was handed over to the Owner by INVESTCORP to put in use in accordance with the expected progress.

The New pressing factory project of Mitsuba M-Tech Vietnam Co. Ltd was commenced in May 2018. After 6 months of construction, the project has been completed, meeting all harsh requirements on quality and progress of the Owner as well as criteria of the Main contractor – Hazama Ando Corporation.

The project is completed successfully and highly appreciated by the Owner and the Main contractor.