Update construction progress of Tamada Office and Warehouse project in July 2019

At the end of July 2019, INVESTCORP Myanmar completed all finishing works for the steel structure of the main factory area and started carrying out acceptance work. Painting of the ceiling and beams of the structure at the first floor has also begun.

At the office area, INVESTCORP Myanmar is conducting gypsum ceiling and partition, painting work, waterproofing, tiling and door installation at the first and second floors.

At the outdoor area, brickwork and plastering of the fence, manholes, drainage ditches and concrete work for the gate have started implementing. Painting of the fence and other outdoor finishing work will be carried out in early September 2019.