In Mar 2019, at the office area, INVESTCORP Myanmar completed beam and slab items of the 1st floor and assembly of roof and surrounding iron fence. Plastering work at the office is being carried out. As expected in Apr 2019, INVESTCORP Myanmar will proceed casting ground slab concrete.
At the warehouse, slab and beam and assembly of steel structure were completed. At present, 50% of assembly work of roof and surrounding fence are being done.
Ancillary items such as guardhouse, pump room, concrete road and gate will be proceeded in Apr 2019. Drainage system, fence and water tanks are being implemented.

Other news
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED