Update construction progress of Tamada Office and Warehouse project in May 2019
At the end of May 2019, INVESTCORP Myanmar completed roof work of the office and workshop areas. The wall corrugated iron has been implemented and is expected to complete in June 2019.
At the outdoor area, INVESTCOPR Myanmar has completed 90% of the plastering work and drainage systems. The ancillary items have been completed all brickwork and began moving to finishing stage. Regarding the internal concrete road, 80% of the workload has been completed currently.
At the office area, INVESTCORP Myanmar has completed 90% of the 1st floor plastering work and is in the process of concreting the 2nd floor’s ground concrete. It is expected that plastering work of the 2nd floor will be carried out and completed by the end of June 2019.
Other news
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED