Update construction progress of Tamada Office and Warehouse project in May 2019

At the end of May 2019, INVESTCORP Myanmar completed roof work of the office and workshop areas. The wall corrugated iron has been implemented and is expected to complete in June 2019.

At the outdoor area, INVESTCOPR Myanmar has completed 90% of the plastering work and drainage systems. The ancillary items have been completed all brickwork and began moving to finishing stage. Regarding the internal concrete road, 80% of the workload has been completed currently.

At the office area, INVESTCORP Myanmar has completed 90% of the 1st floor plastering work and is in the process of concreting the 2nd floor’s ground concrete. It is expected that plastering work of the 2nd floor will be carried out and completed by the end of June 2019.