Update construction progress of Textile dyeing and garment factory project– Ramatex Nam Dinh in May 2019

In May 2019, at the textile area of the Textile dyeing and garment factory project - Ramatex Nam Dinh, INVESTCORP completed erection of the roof steel structures and is carrying out roof work and casting ground concrete. As expected, brickwork and plastering work of the toilet area, power room and compressing room will be implemented and completed in June 2019. Besides, the internal and external putty work of the textile factory’s walls are also implemented in parallel.

At the dyeing area, INVESTCORP has completed construction of the steel structure and is implementing the corrugated iron roof. The ground concrete work is starting being implemented. The toilet area, power room and compressing room will also be proceeded in June 2019.

At the office area, the entire roof work and staircase’s attic have been completed. Currently, INVESTCORP is starting brickwork and plastering work of the 2nd and 3rd floors.