At the end of January 2021, the entire warehouse item at Textile dyeing and garment factory project – Ramatex Nam Dinh phase 2 was completed and handed over to the Investor to put into use.
The Main factory and Canteen have been completed and are in the process of industrial cleaning, internal acceptance before acceptance with the Investor.
The roofing of the Parking house will be completed by INVESTCORP on January 31, 2021. It is expected that the Parking house and other outdoor items such as the concrete road, fence, gate and guard house will be completed on February 7, 2021.
Other news
- Year-end Ceremony 2024 - Welcoming the New Year 2025
- Announcement of Tet Holiday 2025
- Groundbreaking Ceremony of Ding Feng Vietnam Technology Company Limited Factory Project
- Groundbreaking ceremony of Techworld Industries Vietnam factory expansion project
- Seminar to celebrate the 94th anniversary of Vietnamese Women′s Day October 20
- 2024 Independence Day Holiday Announcement
- Handover ceremony of Scouring & Coating area and Congratulations on Autoliv Vietnam project achieving 500,000 safe working hours
- Autoliv’s Chairman visits and works at the Autoliv Vietnam Factory project – Amata Song Khoai Industrial Park – Quang Yen Town – Quang Ninh Province
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED