Update construction progress of Textile dyeing and garment factory project – Ramatex Nam Dinh phase 2 in January 2021
At the end of January 2021, the entire warehouse item at Textile dyeing and garment factory project – Ramatex Nam Dinh phase 2 was completed and handed over to the Investor to put into use.
The Main factory and Canteen have been completed and are in the process of industrial cleaning, internal acceptance before acceptance with the Investor.
The roofing of the Parking house will be completed by INVESTCORP on January 31, 2021. It is expected that the Parking house and other outdoor items such as the concrete road, fence, gate and guard house will be completed on February 7, 2021.



Other news
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED