Update construction progress of Textile dyeing and garment factory project – Ramatex Nam Dinh phase 2 in July 2020
At the end of July 2020, INVESTCORP has completed 50% of the Main factory's structure and has completed the construction of walls at floors 1, 2, and 3 in Zone 1. It is expected that in August 2020, INVESTCORP will finish casting all structural concrete in Zone 2; continue construction of columns, beams, floors 2 and 3 in Zone 3; build brick walls of the 4th floor in Zone 1 and the walls at the 1st floor, 2nd floor of Zone 2.
In the Kitchen and Canteen area, INVESTCORP has completed all columns and is preparing plan for erection of steel structures. In the warehouse area, all concrete of foundation bracing and frame have been completed and INVESTCORP will implement the steel structure erection in August 2020. The outdoor items are being executed at the time with the road foundation, the concrete drainage system and the fence.
All items of the Textile dyeing and garment factory project – Ramatex Nam Dinh are still being constructed by INVESTCORP to follow the overall progress of the project.

- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police