Update construction progress of Vietnam Mie factory project phase 2 in Mar 2019
At the end of Mar 2019, all foundation of the Vietnam Mie factory phase 2 was completed by INVESTCORP. Assembly of columns, trusses and all purlins of the steel structure were also done. Column concrete and wall plastering are started implementing.
The outdoor tanks are completed. Drainage and road are being carried out. All of the construction process ensures requirements before proceeding next works.
It is expected in Apr 2019, INVESTCORP will finish all plastering work to move to finishing works such as tiling, painting, gypsum ceiling… The roof and iron wall will also be completed in Apr 2019.



Other news
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED