Update construction progress of Wearing apparels manufacturing project – Ramatex Hai Phong in Feb 2018
In Feb 2018, the Wearing apparels manufacturing project – Ramatex Hai Phong was continued to be executed by INVESTCORP with their best effort to meet the plan.
In the first ten days of the month, at Block 1, the Contractor had constructed more than 7000m3 of concrete equal to 40,000m2 of beam and slab formwork. Besides, painting and skimcoat work, beam and ceiling, and plastering for brickwork were also continued to implement.
At Block 2, 18,000m2 of floor and entire columns at the 1st floor of the Production building No 3&4, Office building No.2 had been finished to move to the next beam and slap work.
During the Lunar New Year holiday, the whole site and employees were secured by the guards 24/7. Right after the New Year holiday, the project was promtly resume to construct to ensure the project progress.
At present, INVESTCORP continues to complete beam and slab items of the two Blocks and prepare for the following finish work.






- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police




