Update construction progress of Wearing apparels manufacturing project – Ramatex Hai Phong in May 2018
In May 2018, at the Wearing apparels manufacturing project – Ramatex Hai Phong, all items of the Block 1 were urgently implemented by INVESTCORP. Internal and external plastering work have been basically finished. Skimcoat and painting work have been completed up to 80%. At present, tiling work of staircase and toilet, waterproofing work for roof of the office and production buildings are starting to be implemented. Other finishing works such as ceiling, gypsum partition, aluminum cladding, aluminum door and partition are being fabricated and will be installed in June 2018. The office’s elevator has been basically finished installation for commissioning at the beginning of June 2018. Outdoor works such as guardhouse, fence; rainwater and wastewater drainage system are in the process to meet the hand-over schedule of Block 1 at the end of July 2018.
At Block 2, 50% of the slab and beam concrete of the production buildings 3&4 has been completed. Brickwork is also in progress together with grinding and painting work of the beam and ceiling. It is expected, the whole Block 2 will have been finished and handed over to the Owner by the end of 30 November 2018.

- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police