Update construction progress of Wearing apparels manufacturing project – Ramatex Hai Phong
Being commenced on August 17, 2017, the construction status of Wearing apparels manufacturing project – Ramatex Hai Phong after more than 3 months has come into stable and complete all the temporary works such as temporary road, temporary office, workers’ houses, warehouses and temporary electricity system.
At Block 1, piles, concrete foundation, bracing beam for production buildings 1&2 and office building were basically completed. At present, the column concrete and preparation for the foundation concrete work of the first floor are being carried out by the Contractor before moving to the construction stage of beams and slabs of the 2nd floor. In addition, the erection of tower crane for the project execution is also being proceeded in parallel.
At Block 2, mass piling for production buildings 3&4 and office building has been started. Temporary road system for the Block 2 has also been implemented and completed to 80%.
It is expected that the piling work for the entire project will be completed in December 2017 to move to construct beam and slab concrete of the 2nd and 3rd floors of Block 1.









- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police




