Update construction progress – Sankyo project in Apr 2019

Sankyo project was commenced on Feb 27, 2019 consisting of workshop, office and some ancillary items. At present, all temporary works for construction have been completed by INVESTCORP Myanmar.

At the main workshop and office, the foundation, beams and ground are being implemented and are expected to complete in May 2019.

For the outdoor items, construction of drainage system are being carried out at the same time. Form excavation of the internal concrete road is also undertaken.