Update construction progress – Sankyo project in July 2019

In July 2019, INVESTCORP Myanmar speeded up the implementation of all items of the project. At the outdoor area, concrete road and drainage ditches have been basically completed. For the factory, INVESTCORP Myanmar has completed concrete work, plastering work and is carrying out finishing work.

The guard house, power room and pump room have been done. Some other items such as gate, fence, foundation pit and tank system are being executed. Finishing works of the office area and concrete yard have also been completed.

Currently, the project is still being implemented by INVESTCORP Myanmar on schedule and will be handed over to the Owner in September 2019.