Update construction progress – Sankyo project in May 2019

At the end of May 2019, INVESTCORP Myanmar completed the foundation and ground at the office area of the Sankyo project and handed over to the Owner to implement following works.

At the main workshop area, the entire foundation work and 70% of the floor area were completed. The auxiliary items begin to be implemented including pump room, guard house and power room.

At the outdoor area, INVESTCORP Myanmar continues to implement the drainage ditch, internal road, fabrication of fences and gates according to the expected schedule.