Update construction progress – Star Villas project in January 2021
In January 2021, INVESTCORP Myanmar completed and handed over the Villa No. 5 to the Investor for use on January 20, 2021 according to the expected schedule.
The Villas No. 3, 6, 7, 8 & 9 have been completed the reinforced concrete structures and are in progress to erect the roof structure and start plastering and finishing works.
The roof frame structures of the Villa No. 11, 12 & 14 are being implemented simultaneously and are expected to complete in February 2021 to move to the plastering and finishing works.
The Villas No. 15 & 16 are currently waiting for design change from the Investor and will be accelerated construction after getting changed design.
The Villa No. 1B has been constructed in January 2021 and has been completed the pile pressing. In February 2021, the Villa No. 1B will be implemented by INVESTCORP Myanmar to execute the construction of foundation structure and column beams and slabs.


- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police