Update construction progress – Star Villas project in November 2020
In November 2020, INVESTCORP Myanmar completed structural work and is moving to executed finishing work of Villa No.5. As expected, Villa No. 5 will be completed and handed over to the Investor at the end of December 2020.
For the remaining villas, INVESTCORP Myanmar continued to speed up the progress with three piling machines on site to soon complete the piling work and implement the construction of the underground parts. On November 30, 2020, INVESTCORP Myanmar has completed pressing the piles of Villas No. 3, 6, 7, 8, 9 and is proceeding with the next villas. Construction of the foundation has also been quickly implemented and has completed the foundation of the pile base at villas No. 3, 6, 7, and 8.
In December 2020, in addition to completing and handing over Villa No. 5, INVESTCORP Myanmar will also speed up the pile foundation of the remaining 9 villas, complete the entire foundation bracing for 13 villas, complete concrete on the first floor for 9 out of 13 villas, complete column concrete on the first floor for 6 out of 13 villas and implement fabrication and erection of reinforced formwork on the first floor for 4 out of 13 units.


- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police