Update construction progress – Traditional building project of Tho Xuan district in Mar 2020
By the end of March 2020, INVESTCORP LAND Thanh Hoa had completed the concreting of attic roof and staircase at both sides; basically installed the electrical system and groundwater of the building, completed brickwork of the column system and technical boxes and internal plastering of the 1st, 2nd and 3rd floors. All aluminum and glass materials, floor tiles have been gathered at the site for construction.
At the present time, INVESTCORP Land Thanh Hoa is carrying out construction of the stairs’ brickwork and plastering the exterior of the house, installing the gypsum ceiling, dismantling the dust grid and preparing to paint the walls and install glass for the building.
It is expected that in April 2020, the remaining finishing works such as plastering, tiling the floor and front lobby area, installing gypsum ceiling, installing glass wall frame and cleaning work will be completed to inspect and hand over to the Investor.

- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police