After nearly one month of construction, INVESTCORP Land Thanh Hoa has done all temporary works for the Traditional building project of Tho Xuan district including temporary office and worker accommodation.

At present, INVESTCORP Land Thanh Hoa has completed the foundation and is executing backfilling and foundation levelling.

According to the plan in Dec 2019, INVESTCORP Land Thanh Hoa will speed up finish work of underground water tank, finish of the 1st floor and construction of the 2nd floor’s columns.