Update construction progress – Yukioh factory project in January 2020
In Jan 2020, INVESTCORP Myanmar completed the brickwork and prepared construction of the gypsum work of the office; completed the floor concrete and prepared construction of the gypsum work of the factory.
Wastewater treatment tank has been completed the wall concrete and is carried out the formwork and reinforcement bar of the tank’s cap. Surrounding walls of the pump room and power room are done by INVESTCORP Myanmar. The fence is executed foundation poles, foundation beam and installation of the fence’s frame.
It is expected in Feb 2020, INVESTCORP Myanmar will continue constructing and finishing the factory area, speeding up construction of light load road, drainage ditches, pit foundation and wastewater treatment system.


Other news
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED