Update construction progress – Yukioh factory project in Nov 2019
In Nov 2019, INVESTCORP Myanmar executed plastering work of the office, formwork, rebar and ground concrete of the workshop. The entire internal road of heavy load, foundation of the wastewater treatment tanks and Pit system have been completed.
At present, INVESTCORP Myanmar is carrying out light load road, executing fence foundation and fabrication of fence frame.
In Dec 2019, INVESTCORP Myanmar will speed up execution of the wastewater treatment tanks, water tanks and other auxiliary tanks; finish of drainage system etc.


Other news
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED