Update construction progress – Yukioh factory project in Oct 2019
By the end of Oct 2019, at the main workshop, INVESTCORP Myanmar has been carrying out assembly of main structure, sand levelling and workshop’s ground compact. At the office area, assembly of main structure is also executed in parallel with the fabrication of formwork and assembly of ground reinforcement.
Currently, INVESTCORP Myanmar continues executing and completing the internal road of heavy load and prepare to implement the light load one. The foundation excavation, pile head cutting, reinforcement fabrication of the drainage system and the factory water tanks are in progress.
It is expected that in November 2019, INVESTCORP Myanmar will accelerate the construction of wastewater treatment system, water tanks and other auxiliary tanks; constructing drainage ditch system etc.

- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police