Construction progress updated in October 2023 - Technical Infrastructure Project of Residential Area in Phu Xuan Commune, Tho Xuan District
In October 2023, INVESTCORP Land Thanh Hoa Company carried out the construction of items and volumes according to the contract.
For transportation, weathering excavation reached 15% of the volume and 13% of the volume of K95 soil embankment. The fabrication of precast components reached 5% of the contract volume.
.jpg)
.jpg)
As planned in November 2023, INVESTCORP Land Thanh Hoa Company will focus on implementing the construction of traffic items, speeding up K95 excavation work, and carrying out drainage system construction to ensure the project's quality and progress.
.jpg)
.jpg)
As planned in November 2023, INVESTCORP Land Thanh Hoa Company will focus on implementing the construction of traffic items, speeding up K95 excavation work, and carrying out drainage system construction to ensure the project's quality and progress.
Other news
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED