Construction progress updated in October 2023 – Sao Mai Resort Project, Tho Lam Commune – Tho Xuan District – Thanh Hoa Province
In October 2023, INVESTCORP 6 Company continued to carry out the construction and finishing items of the Sao Mai Resort project, Tho Lam commune - Tho Xuan district - Thanh Hoa province.
For the 18 villas and reception house, tennis court, laundry house, and the two powerhouses, INVESTCORP 6 has completed all and is waiting for acceptance and handover for use.
.jpg)
For the five Family villas, building work has been completed and finishing work is in progress.
.jpg)
It is expected that in November 2023, INVESTCORP 6 will complete the finishing work for the five Family villas and carry out the acceptance and handover of the 18 villas, reception house, tennis court, laundry house, and the two powerhouses.
.jpg)
For the five Family villas, building work has been completed and finishing work is in progress.
.jpg)
It is expected that in November 2023, INVESTCORP 6 will complete the finishing work for the five Family villas and carry out the acceptance and handover of the 18 villas, reception house, tennis court, laundry house, and the two powerhouses.
Other news
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED