Cập nhật tiến độ thi công tháng 07/2022 - Dự án Xây dựng Nhà máy mới cho Công ty TNHH AIR WATER Việt Nam tại Hà Nam

In July 2022, INVESTCORP 15 has completed all construction items in the factory area. The works of building, plastering, tiling and dismantling the scaffolding covering the office area are being implemented by INVESTCORP 15. The water tank area and pump room were completed and handed over to the contractor to install equipment and pump water into the tank for testing.

In August 2022, INVESTCORP 15 together with the main contractor carried out the acceptance and handover to the Investor for use.

 