Construction progress updated in March 2023 – Key Technology Hanoi Factory Project Phase 2
By the end of March 2023, INVESTCORP 9 has completed 60% of the project's workload, including backfilling and lining for the factory floor reached 60%, plastering the factory wall reached 90%; completed 100% of the foundation base and house column painting; completed concrete pouring of the foundation floor and erected steel columns for the garbage house; completed steel erection and roof beam formwork.
According to the plan in April 2023, INVESTCORP 9 will mainly focus on pouring concrete for the factory floor and pumping house and implementing finishing works for toilets. It is expected that by the end of April 2023, INVESTCORP 9 will complete 90% of the project workload.

Other news
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED