Construction progress updated in November 2021 – Design and build project of Welco Technology Vietnam Factory
At the end of November 2021, at the Design and build project of Welco Technology Vietnam Factory, INVESTCORP 9 has completed all the pile pressing work and 80% of the foundation frame and bracing. The foundation work is expected to be completed on December 5, 2021.
Currently, INVESTCORP 9 is in the process of leveling and pouring concrete for the foundation. The columns, beams and slabs on the 2nd floor will also be proceeded successively according to the construction progress of the foundation.
Outdoor underground items such as wastewater treatment tanks, septic tanks, and water tanks are being carried out in parallel with the foundation of the main house. It is expected that auxiliary items such as security house, chemical warehouse, garbage house etc. will be executed in December 2021 to ensure completion at the same time as the main house.

- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
- INVESTCORP Group Organizes Annual Employee Health Check-up Program 2025
- INVESTCORP Group – 15 Years of Journey, Achievements, and Aspirations
- INVESTCORP Group celebrates the 95th anniversary of Vietnamese Women′s Day