Construction progress of Biel Crystal Vietnam Factory Project in August 2017
For each project, besides important factors of safety and quality, progress is also a very important one. Therefore, the construction Contractor- INVESTCORP always tries its best not only to ensure the three above-mentioned factors but also to complete the project beyond planned progress and the Biel Crystal Vietnam Factory project is an example. As expected, the whole Factory will be handed-over to the Owner and put into use in this September 2017.
As of the end of August 2017, all construction items have been basically completed: Factory ground, concrete of brace, beam and column, etc. Other items such as structural installation, building office walls, plastering workshop walls have also been done up to 80%.
The whole Factory is expected to be completed in September 2017: Completion of the remaining walls, plastering walls of both the workshop and the office area, completion of steel structure and metal roof, painting finish for the whole workshop and tiling finish.
- Congratulations to VDL ETG Group (Netherlands) on inauguration of its first factory in Vietnam
- INVESTCORP Group welcomes and works with the delegation from the German Chamber of Commerce and Industry (IHK) Region Stuttgart
- Groundbreaking Ceremony of staBOO Thanh Hoa OSB Bamboo Board Manufacturing Plant
- Announcement of Holiday schedule for Apr 30 and May 1, 2025
- Seminar to celebrate International Women′s Day March 8
- Spring travel of At Ty 2025
- INVESTCORP Group opens the spring of year At Ty 2025
- Year-end Ceremony 2024 - Welcoming the New Year 2025