News

Update construction progress – Phase 4 factory construction project of Yokowo Vietnam Co., Ltd in August 2020

Update construction progress – Phase 4 factory construction project of Yokowo Vietnam Co., Ltd in August 2020

At the end of Aug 2020, INVESTCORP has completed all concrete foundation for the expanded area of the Main factory - Phase 4 factory construction project of Yokowo Vietnam Co., Ltd and started the construction of gypsum ceiling. It is expected ...
Update construction progress of Textile dyeing and garment factory project – Ramatex Nam Dinh phase 2 in August 2020

Update construction progress of Textile dyeing and garment factory project – Ramatex Nam Dinh phase 2 in August 2020

In August 2020, INVESTCORP completed all the concrete structures in Zone 1, Zone 2 and the wall construction in Zone 1 of the Main factory of the Textile dyeing and garment factory project – Ramatex Nam Dinh phase 2. It is ...
Update construction progress – Lakeside Service Apartment (Myanmar) project in August 2020

Update construction progress – Lakeside Service Apartment (Myanmar) project in August 2020

At the end of August 2020, the Lakeside Service Apartment (Myanmar) project continued to be piled by INVESTCORP Myanmar and started excavation work, installed shoring system and cut bored pile heads. Currently, INVESTCORP Myanmar has completed 85% of the piling works ...
Update construction progress – Crystal Martin Vietnam factory project in August 2020

Update construction progress – Crystal Martin Vietnam factory project in August 2020

Crystal Martin Vietnam factory project is located in Quang Chau Industrial Park - Viet Yen - Bac Giang, consisting of the two items of domestic wastewater treatment station and renovation of the 6th floor of R1C building into an office.
Handover of Meiko Quang Minh electronics assembling factory project

Handover of Meiko Quang Minh electronics assembling factory project

At the end of August 2020, all items of Meiko Quang Minh electronics assembling factory project were completed by INVESTCORP. Currently, the project is being inspected and handed over to the Investor - Meiko Electronics Vietnam Co., Ltd.
Update construction progress – Phase 4 factory construction project of Yokowo Vietnam Co., Ltd in July 2020

Update construction progress – Phase 4 factory construction project of Yokowo Vietnam Co., Ltd in July 2020

In July 2020, at the Phase 4 factory construction project of Yokowo Vietnam Co., Ltd, construction items continued to be carried out by INVESTCORP to catch up with the progress submitted to the Investor.
Updated construction progress - Electrical decoration project of Cau Ke street in July 2020

Updated construction progress - Electrical decoration project of Cau Ke street in July 2020

At the end of June 2020, INVESTCORP Land Thanh Hoa completed installation of the remaining two double light poles and connected electricity for the whole line to run commission on June 28, 2020. On July 10, 2020, the project was officially ...
Update construction progress in July 2020 – Embellishment project of Rung Thong historic sites and landscapes

Update construction progress in July 2020 – Embellishment project of Rung Thong historic sites and landscapes

In July 2020, INVESTCORP Land Thanh Hoa mobilized necessary resources to complete the project and handed it over to the Investor to hold the project inauguration ceremony before the XXV Party Congress of Dong Son district for the term 2020-2025.
Update construction progress – Lakeside Service Apartment (Myanmar) project in July 2020

Update construction progress – Lakeside Service Apartment (Myanmar) project in July 2020

INVESTCORP Myanmar is now executing piling work for the basement construction of the Lakeside service apartment (Myanmar) project.
Update construction progress – Meiko Quang Minh electronics assembling factory project in July 2020

Update construction progress – Meiko Quang Minh electronics assembling factory project in July 2020

In July 2020, INVESTCORP continued its efforts to carry out the Meiko Quang Minh electronics assembling factory project to hand over to the Investor on time.