Update construction progress of Textile dyeing and garment factory project– Ramatex Nam Dinh in September 2019

Update construction progress of Textile dyeing and garment factory project– Ramatex Nam Dinh in September 2019

By the end of September 2019, INVESTCORP has completed the entire construction work at the dyeing workshop and handed it to the Owner to implement installation of the machine.
Update construction progress – Yukioh factory project in September 2019

Update construction progress – Yukioh factory project in September 2019

In September 2019, INVESTCORP Myanmar has completed some items of the factory, including the foundation system and bracing beams of the main workshop and office building. Currently, the internal roads, factory gates and areas connecting with the industrial zone are being ...
Update construction progress of Tamada Office and Warehouse project in September 2019

Update construction progress of Tamada Office and Warehouse project in September 2019

In September 2019, at the Tamada Office and Warehouse project, INVESTCORP Myanmar has completed 100% of the finishing work of the main workshop and is carrying out cleaning.
Handover of Sankyo project

Handover of Sankyo project

By the end of September 2019, INVESTCORP Myanmar has completed finishing work for the entire Sankyo project and handed over to the Owner.
Handover of Golden Land Project Pharmaceutical Factory

Handover of Golden Land Project Pharmaceutical Factory

By the end of September 2019, finishing of remaining works of the Golden Land Project Pharmaceutical Factory such as curb system, internal road, roof structural assembly etc. have been done by INVESTCORP Myanmar.
1st establishment anniversary of member company – INVVESTCORP Land Thanh Hoa Company Ltd

1st establishment anniversary of member company – INVVESTCORP Land Thanh Hoa Company Ltd

On Sep 19, 2019, the 1st establishment anniversary of the member company – INVESTCORP Land Thanh Hoa Company Ltd was held by Investment and development Construction Industrial Corporation INVESTCORP at its headquarters at Lot A15-16, Van Phuc auction land, Van Phuc ...
Update construction progress of Textile dyeing and garment factory project– Ramatex Nam Dinh in August 2019

Update construction progress of Textile dyeing and garment factory project– Ramatex Nam Dinh in August 2019

By the end of August 2019, at the dyeing area, INVESTCORP has completed the entire construction and handed over to the Owner.
Update construction progress – Yukioh factory project in Aug 2019

Update construction progress – Yukioh factory project in Aug 2019

By the end of August 2019, INVESTCORP Myanmar has completed site clearance and construction of temporary items for the Yukioh Factory project including roads, fences, gates etc.
Update construction progress of Tamada Office and Warehouse project in August 2019

Update construction progress of Tamada Office and Warehouse project in August 2019

In August 2019, finishing work of the main factory of Tamada office and warehouse project was completed up to 95%.
Update construction progress – Sankyo project in August 2019

Update construction progress – Sankyo project in August 2019

In Aug 2019, INVESTCORP Myanmar implemented finishing works of the outdoor road and ground slab. The workshop has been completed the machine platform and are moving to painting finishing stage and door installation. Finishing work of the office and concrete yard ...