Construction progress updated in March 2023 – Sakata Inx Vietnam Factory Project - Bac Ninh Branch

Construction progress updated in March 2023 – Sakata Inx Vietnam Factory Project - Bac Ninh Branch

In March 2023, INVESTCORP 15 completed auxiliary works including internal asphalt spreading and surrounding grass planting. In parallel, both main factory package and auxiliary factory package are also cleaned and repaired outstanding defects by INVESTCORP 15.
Construction progress updated in March 2023 – Sao Mai Lam Son - Sao Vang New Urban Area Project, Xuan Thang Commune, Tho Xuan District, Thanh Hoa Province

Construction progress updated in March 2023 – Sao Mai Lam Son - Sao Vang New Urban Area Project, Xuan Thang Commune, Tho Xuan District, Thanh Hoa Province

In March 2023, INVESTCORP 6 continued to construct the items under the contract including leveling the ground, pouring concrete, installing curb stones, paving pavements, completing manholes and around flower beds. Accumulated construction volume by the end of March 2023 reached 35%.
Construction progress updated in March 2023 - Renovation and upgrading project of provincial road 506B, section from Tho Lap commune to Xuan Tin commune, Tho Xuan district

Construction progress updated in March 2023 - Renovation and upgrading project of provincial road 506B, section from Tho Lap commune to Xuan Tin commune, Tho Xuan district

At the beginning of March 2023, INVESTCORP Land Thanh Hoa gathered machinery and human resources to carry out the construction of work items according to the signed contract.
A Talk to celebrate International Women's Day 8/3

A Talk to celebrate International Women's Day 8/3

Joining the joyful atmosphere to celebrate International Women's Day, on the morning of March 8, 2023, INVESTCORP Group held a talk at its headquarters. Attending the talk was the Group's Board of Directors, heads of departments and especially all female staff working at the Group's Office.
Construction progress updated in  February 2023 – Key Technology Hanoi Factory Project Phase 2

Construction progress updated in February 2023 – Key Technology Hanoi Factory Project Phase 2

By the end of February 2023, INVESTCORP 9 has completed the construction of reinforced concrete structures including foundations, foundation beams and columns of the factory and water tank.
Construction progress updated in February 2023 - TOYO INK COMPOUNDS Vietnam Factory Project Phase 3

Construction progress updated in February 2023 - TOYO INK COMPOUNDS Vietnam Factory Project Phase 3

By the end of February 2023, INVESTCORP 10 has completed the temporary erection works for construction and completed 100% of the pile pressing and compression test for the main factory and warehouse.
Construction progress updated in February 2023 - Vina Ito Factory Project Phase 2

Construction progress updated in February 2023 - Vina Ito Factory Project Phase 2

In February 2023, INVESTCORP 15 has completed building and plastering the factory walls, constructing layer 1 of the internal road and rainwater drainage system. Along with that, the construction of the garbage house walls and the installation of V steels for manhole covers are also being implemented by INVESTCORP 15.
Construction progress updated in February 2023 – Sakata Inx Vietnam Factory Project - Bac Ninh Branch

Construction progress updated in February 2023 – Sakata Inx Vietnam Factory Project - Bac Ninh Branch

In February 2023, for the main factory package, the remaining works such as tiling, mechanics and foundations for machines of all kinds have been completed by INVESTCORP 15. For the exterior package, INVESTCORP 15 has also completed the handover of ancillary items, is implementing internal roads and installing sidewalk curbs.
Construction progress updated in February 2023 – Dai Lai Eco-Residence and Resort Project, Ngoc Thanh Commune, Phuc Yen City, Vinh Phuc Province

Construction progress updated in February 2023 – Dai Lai Eco-Residence and Resort Project, Ngoc Thanh Commune, Phuc Yen City, Vinh Phuc Province

In February 2023, IVC Creation Company continues to execute the bidding package "Construction of earth retaining wall" under the project "Dai Lai Eco-Residence and Resort".
Construction progress updated in February 2023 – Residential Area Technical Infrastructure Project in Quang Dong Commune, Thanh Hoa City, Thanh Hoa Province

Construction progress updated in February 2023 – Residential Area Technical Infrastructure Project in Quang Dong Commune, Thanh Hoa City, Thanh Hoa Province

In February 2023, INVESTCORP Land Thanh Hoa has focused on implementing the construction of project items under the contract.
Construction progress updated in February 2023 – Typical Residential Area Infrastructure Project in Hoang Hoc Village, Dong Hoang Commune, Dong Son District, Thanh Hoa Province

Construction progress updated in February 2023 – Typical Residential Area Infrastructure Project in Hoang Hoc Village, Dong Hoang Commune, Dong Son District, Thanh Hoa Province

In February 2023, INVESTCORP Land Thanh Hoa has completed 100% of the asphalt irrigation to adhere to the road surface and asphalt pavement.
Construction progress updated in February 2023 - Project of renovating and upgrading rescue road in Truong Xuan commune to left dike of Chu river, Tho Xuan district, Thanh Hoa province

Construction progress updated in February 2023 - Project of renovating and upgrading rescue road in Truong Xuan commune to left dike of Chu river, Tho Xuan district, Thanh Hoa province

In February 2023, INVESTCORP Land Thanh Hoa continues to implement the construction of items and workloads according to the contract. The works performed during the month include drainage and lighting items.
Construction progress updated in February 2023 – Sao Mai Resort Project, Tho Lam Commune – Tho Xuan District – Thanh Hoa Province

Construction progress updated in February 2023 – Sao Mai Resort Project, Tho Lam Commune – Tho Xuan District – Thanh Hoa Province

In February 2023, INVESTCORP 6 continues to construct and complete items such as reception area, Rubby Four Seasons villa area, Bungalow under the lake and other ancillary items.
Construction progress updated in February 2023 – Sao Mai Lam Son - Sao Vang New Urban Area Project, Xuan Thang Commune, Tho Xuan District, Thanh Hoa Province

Construction progress updated in February 2023 – Sao Mai Lam Son - Sao Vang New Urban Area Project, Xuan Thang Commune, Tho Xuan District, Thanh Hoa Province

In February 2023, INVESTCORP 6 continues to execute the works under the contract, including leveling the ground, pouring concrete, installing curbs, paving pavements and completing the locations of manholes for water collection and flower beds around.
Construction progress updated in January 2023 - Vina Ito Factory Project Phase 2

Construction progress updated in January 2023 - Vina Ito Factory Project Phase 2

In January 2023, INVESTCORP 15 has completed 70% of the work volume of the factory concrete floor, the remaining 30% of the volume is temporarily stopped to wait for the Investor’s design change. In addition, the construction of internal roads, storm water drainage system and garbage houses are also being urgently implemented by INVESTCORP 15.