Construction progress updated in September 2022 – Sakata Inx Vietnam Factory Project - Bac Ninh Branch

Construction progress updated in September 2022 – Sakata Inx Vietnam Factory Project - Bac Ninh Branch

On September 14, 2022, Investor Sakata and Main contractor Nishimatsu held the groundbreaking ceremony to officially started the construction work under the contract.
Construction progress updated in September 2022 – Expansion project of Meiko Quang Minh manufacturing and assembling electronic components factory - Phase 1

Construction progress updated in September 2022 – Expansion project of Meiko Quang Minh manufacturing and assembling electronic components factory - Phase 1

At the end of September 2022, INVESTCORP Dong Minh has completed the construction of items of the PCB building such as construction of the 2nd floor columns, the 3rd floor beams, the 3rd floor columns, the roof floor beams, the attic beams, and dismantling formwork of beams and slabs.
4th Anniversary of INVESTCORP Land Thanh Hoa Company Limited

4th Anniversary of INVESTCORP Land Thanh Hoa Company Limited

On the afternoon of September 17, 2022, INVESTCORP Land Thanh Hoa Company Limited solemnly held a ceremony to celebrate 4 years of establishment at Dai Viet palace – Wedding & Convention in Thanh Hoa city. The ceremony was presented by the Group's Board of Directors, Directors of member companies and all employees of INVESTCORP Land Thanh Hoa.
Construction progress updated in August 2022 – Project of Repairing damage to foundation, road surface, drainage system and traffic safety at section Km51+600 - Km53+500; Km57+00 - Km59+700, National way 47, Thanh Hoa province

Construction progress updated in August 2022 – Project of Repairing damage to foundation, road surface, drainage system and traffic safety at section Km51+600 - Km53+500; Km57+00 - Km59+700, National way 47, Thanh Hoa province

In August, 2022, INVESTCORP Land Thanh Hoa Company Limited focused on speeding up the construction progress and basically completed the items such as construction of road mold excavation, compaction, reinforcement and expansion of roadside, and spreading crushed stone to widen the roadside.
Construction progress updated in August 2022 – Technical infrastructure project of residential area in Quang Dong commune, Thanh Hoa city, Thanh Hoa province

Construction progress updated in August 2022 – Technical infrastructure project of residential area in Quang Dong commune, Thanh Hoa city, Thanh Hoa province

In August 2022, INVESTCORP Land Thanh Hoa Company Limited focused on executing the project items under the contract. Construction works during the month includes road surface leveling and repair, compaction and land restitution of K98 soil; rainwater drainage system and processing and casting of concrete components reached 96%. Total volume is estimated at 26% of contract volume.
Construction progress update in August 2022 – Typical Residential Area Infrastructure Project in Hoang Hoc Village, Dong Hoang Commune, Dong Son District, Thanh Hoa Province

Construction progress update in August 2022 – Typical Residential Area Infrastructure Project in Hoang Hoc Village, Dong Hoang Commune, Dong Son District, Thanh Hoa Province

In August 2022, INVESTCORP Land Thanh Hoa Company Limited focused on implementing the construction of items including 43% of asphalt spreading on roads No. 1, 2, 5, 6 & 9. At the same time, the Company has completed the construction and installation of road surface drainage and drainage ditches. Total construction volume reached 83% of the contract volume.
Construction progress update in August 2022 – Road project from Xuan Hung commune connecting with road from Tho Xuan town to Lam Son – Sao Vang urban area, Tho Xuan district

Construction progress update in August 2022 – Road project from Xuan Hung commune connecting with road from Tho Xuan town to Lam Son – Sao Vang urban area, Tho Xuan district

In August 2022, INVESTCORP Land Thanh Hoa Company Limited continued to implement items related to K98 road surface. The volume of work done in the month includes completion of K98 road surface compaction 1st layer, 50% of K98 soil work, 40% of rock embankment work, transportation of 40% of weathered soil to the collection ground. At the same time, INVESTCORP Land Thanh Hoa focused on constructing the drainage system, casting components and completing 90% of the work volume.
Construction progress updated in August 2022 – Expansion project of Meiko Quang Minh manufacturing and assembling electronic components factory - Phase 1

Construction progress updated in August 2022 – Expansion project of Meiko Quang Minh manufacturing and assembling electronic components factory - Phase 1

In August 2022, INVESTCORP Dong Minh has completed the construction of items at the PCB building, including construction of foundation, ground and floor beam construction on the 2nd floor. The works are being carried out such as construction of the 3rd floor beams, 3rd floor column construction, roof floor beams and slabs and roof floor columns.
Construction progress updated in August 2022 - New An Nam Matsuoka Garment Factory project – Phase 3B

Construction progress updated in August 2022 - New An Nam Matsuoka Garment Factory project – Phase 3B

In August 2022, INVESTCORP 9 has completed all the work of pouring concrete for the main factory.
Completion and handover of New Factory Construction Project of AIR WATER Vietnam Co., Ltd in Ha Nam

Completion and handover of New Factory Construction Project of AIR WATER Vietnam Co., Ltd in Ha Nam

The New Factory Construction Project of AIR WATER Vietnam Co., Ltd in Ha Nam has been constructed by INVESTCORP 15 since February 2022. After 7 months of construction, INVESTCORP 15 has completed all construction items as per the contract signed with main contractor. On August 23, 2022, INVESTCORP 15 together with the main contractor carried out the acceptance work and handed over the Project to the Investor and put it into use.
INVESTCORP holds a friendly football match between member companies

INVESTCORP holds a friendly football match between member companies

The friendly match was exciting with the spirit of exchange but equally fierce, both teams tried to create beautiful balls. In particular, the match was held after working hours, so all employees of member companies were present to cheer for the teams. After the friendly match ended, the employees of the member companies held a party so that everyone could share with each other about their work and personal life in order to improve the spirit of solidarity and sharing among the member companies.
Construction progress updated in July 2022 – Expansion project of Meiko Quang Minh manufacturing and assembling electronic components factory - Phase 1

Construction progress updated in July 2022 – Expansion project of Meiko Quang Minh manufacturing and assembling electronic components factory - Phase 1

At the end of July 2022, the items of PCB building have been completed by INVESTCORP Dong Minh including construction of reinforcement, formworks, and concrete pouring after more than two months of commencement of the Expansion project of Meiko Quang Minh manufacturing and assembling electronic components factory - Phase 1 of Meiko Electronics Quang Minh Co., Ltd. Other finishing works are under construction such as leveling, compaction, 1st floor columns and 2nd floor beams.
Construction progress updated in July 2022 - New An Nam Matsuoka Garment Factory project – Phase 3B

Construction progress updated in July 2022 - New An Nam Matsuoka Garment Factory project – Phase 3B

In July 2022, INVESTCORP 9 has completed the entire construction of reinforced concrete for columns and walls of the main house category including foundation concrete casting and roofing which are being implemented in parallel.
Construction progress updated in July 2022 - New Factory Construction Project of AIR WATER Vietnam Co., Ltd in Ha Nam

Construction progress updated in July 2022 - New Factory Construction Project of AIR WATER Vietnam Co., Ltd in Ha Nam

In July 2022, INVESTCORP 15 has completed all construction items in the factory area. The works of building, plastering, tiling and dismantling the scaffolding covering the office area are being implemented by INVESTCORP 15. The water tank area and pump room were completed and handed over to the contractor to install equipment and pump water into the tank for testing.
Construction progress updated in July 2022 – Technical infrastructure project of residential area in Quang Dong commune, Thanh Hoa city, Thanh Hoa province

Construction progress updated in July 2022 – Technical infrastructure project of residential area in Quang Dong commune, Thanh Hoa city, Thanh Hoa province

In July 2022, INVESTCORP Land Thanh Hoa Co., Ltd. has implemented the works including: construction of K98 embankment of roads reached 83%; installation of surface water drainage system reached 63%; fabricating, casting and pouring curb concrete reached 90% of the volume.