Construction progress update in November 2022 – Road project from Xuan Hung commune connecting with road from Tho Xuan town to Lam Son – Sao Vang urban area, Tho Xuan district
In November 2022, INVESTCORP Land Thanh Hoa Company Limited continued to organize the construction of the items under the contract. The works performed in the month include traffic items and sewers.
For the traffic items, INVESTCORP Land Thanh Hoa has implemented the K98 embankment work, the tray foot, and the stone roof embankment reached 97%; the transportation of weathered soil to the disposal site reached 90%. At the same time, INVESTCORP Land Thanh Hoa has also constructed 90% of the horizontal sewer.
As planned in December 2022, INVESTCORP Land Thanh Hoa continues to implement the construction of works related to the road surface, completing the K98 earthwork, embankment work, crushed stone foundation 4x6 and spreading asphalt layer, completing signpost system, and installing drainage system.
- Announcement of Holiday schedule for Apr 30 and May 1, 2024
- Autoliv’s Chairman visits and works at the Autoliv Vietnam Factory project – Amata Song Khoai Industrial Park – Quang Yen Town – Quang Ninh Province
- Discussion program to celebrate the 114th anniversary of International Women′s Day March 8
- Groundbreaking ceremony of Jehong Textile Factory Project
- Enjoy spring of the new year Giap Thin 2024
- INVESTCORP Group begins the Spring of the Dragon year 2024
- INVESTCORP Group organizes the Year-End Party 2023 – Happy New Year 2024
- Announcement of Tet Holiday 2024