Construction progress update in November 2022 – Road project from Xuan Hung commune connecting with road from Tho Xuan town to Lam Son – Sao Vang urban area, Tho Xuan district

In November 2022, INVESTCORP Land Thanh Hoa Company Limited continued to organize the construction of the items under the contract. The works performed in the month include traffic items and sewers.

For the traffic items, INVESTCORP Land Thanh Hoa has implemented the K98 embankment work, the tray foot, and the stone roof embankment reached 97%; the transportation of weathered soil to the disposal site reached 90%. At the same time, INVESTCORP Land Thanh Hoa has also constructed 90% of the horizontal sewer.

As planned in December 2022, INVESTCORP Land Thanh Hoa continues to implement the construction of works related to the road surface, completing the K98 earthwork, embankment work, crushed stone foundation 4x6 and spreading asphalt layer, completing signpost system, and installing drainage system.