Construction progress updated in October 2022 – Project of Repairing damage to foundation, road surface, drainage system and traffic safety at section Km51+600 - Km53+500; Km57+00 - Km59+700, National way 47, Thanh Hoa province

In October 2022, INVESTCORP Land Thanh Hoa Company Limited has focused on speeding up the construction progress of the items in the contract. Items are under construction including drainage system, repairing damaged pavement, and traffic safety.

For the drainage system, INVESTCORP Land Thanh Hoa has constructed 95% of the excavation and installation of trench components. In addition, roughening the road surface has been completed, the adhesive watering and asphalt spreading have reached 50%. Total volume is estimated at 58% in compared with the contract plan.

As planned in November 2022, INVESTCORP Land Thanh Hoa will continue to speed up the construction progress to basically complete the construction volume under the contract.