Construction progress updated in May 2023 - Project of renovating and upgrading rescue road in Truong Xuan commune to left dike of Chu River, Tho Xuan district, Thanh Hoa province

In May 2023, INVESTCORP Land Thanh Hoa completed the construction of 100% of the drainage system and lighting items.

In addition, for the road surface, the Company also completed the construction of crushed stone and asphalt pavement. Total construction output is estimated at 50% of the contract volume.

As planned in June 2023, INVESTCORP Land Thanh Hoa will focus on implementing the construction of asphalt pavement for the whole project.


 