Construction progress updated in May 2023 - Renovation and upgrading project of provincial road 506B, section from Tho Lap commune to Xuan Tin commune, Tho Xuan district

In May 2023, INVESTCORP Land Thanh Hoa excavated and transported weathered soil with 43% of the work volume; transported and embanked the K95 reached 18% of the volume. For the drainage system, the Company is implementing the construction of horizontal culvert steel.

As planned in June 2023, INVESTCORP Land Thanh Hoa will focus on carrying out the construction of the road surface, speeding up the excavation of weathering soil, embankment of K95 for the whole road, and at the same time implementing the construction of the drainage system.