Construction progress updated in May 2023 – Road project from Xuan Hung commune connecting with road from Tho Xuan town to Lam Son – Sao Vang urban area, Tho Xuan district

By the end of May 2023, INVESTCORP Land Thanh Hoa has constructed 100% of asphalt pavement, asphalt concrete spreading with 100% of the volume, and construction of crushed stone for horizontal roads reaches 100%. Total construction output is estimated at 89% of the contract volume.

As planned in June 2023, the Company will focus on completing the construction of horizontal roads and traffic safety items.