Construction progress updated in May 2023 – Road project from Xuan Hung commune connecting with road from Tho Xuan town to Lam Son – Sao Vang urban area, Tho Xuan district
By the end of May 2023, INVESTCORP Land Thanh Hoa has constructed 100% of asphalt pavement, asphalt concrete spreading with 100% of the volume, and construction of crushed stone for horizontal roads reaches 100%. Total construction output is estimated at 89% of the contract volume.
As planned in June 2023, the Company will focus on completing the construction of horizontal roads and traffic safety items.
Other news
- Autoliv’s Chairman visits and works at the Autoliv Vietnam Factory project – Amata Song Khoai Industrial Park – Quang Yen Town – Quang Ninh Province
- Announcement of Holiday schedule for Apr 30 and May 1, 2024
- Discussion program to celebrate the 114th anniversary of International Women′s Day March 8
- Groundbreaking ceremony of Jehong Textile Factory Project
- Enjoy spring of the new year Giap Thin 2024
- INVESTCORP Group begins the Spring of the Dragon year 2024
- INVESTCORP Group organizes the Year-End Party 2023 – Happy New Year 2024
- Announcement of Tet Holiday 2024
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED