Construction progress updated in May 2023 – An additional tender package under item

In May 2023, INVESTCORP 15 completed the erection of drywall frames, gypsum ceiling frames, toilet wall tiles, stair paving, and electrical wiring for sockets and lighting systems.

At the same time, the Company is also implementing items such as the construction of drywalls reached 80%, the installation of gypsum ceiling panels reached 80%, painting walls and ceilings reached 50%, and 40% of floor tile installation. In addition, the erection of glass walls and installation of curtains have also started to be implemented by the Company.

It is expected that in June 2023, all of the construction and installation work will be 100% completed by INVESTCORP 15.It is expected that in June 2023, all of the construction and installation work will be 100% completed by INVESTCORP 15.


 