Construction progress updated in September 2023 – Sao Mai Resort Project, Tho Lam Commune – Tho Xuan District – Thanh Hoa Province

Construction progress updated in September 2023 – Sao Mai Resort Project, Tho Lam Commune – Tho Xuan District – Thanh Hoa Province

At the end of September 2023, INVESTCORP 6 continued to implement items under the Sao Mai Resort project, Tho Lam commune - Tho Xuan district - Thanh Hoa province.
Construction progress updated in September 2023 - Renovation and upgrading project of provincial road 506B, section from Tho Lap commune to Xuan Tin commune, Tho Xuan district

Construction progress updated in September 2023 - Renovation and upgrading project of provincial road 506B, section from Tho Lap commune to Xuan Tin commune, Tho Xuan district

In September 2023, INVESTCORP Land Thanh Hoa continued to focus on mobilizing machinery and human resources to implement construction items under the Renovation and upgrading project of provincial road 506B, the section from Tho Lap commune to Xuan Tin commune, Tho Xuan district.
Construction progress updated in September 2023 - Technical Infrastructure Project of Residential Area in Phu Xuan Commune, Tho Xuan District

Construction progress updated in September 2023 - Technical Infrastructure Project of Residential Area in Phu Xuan Commune, Tho Xuan District

In September 2023, the Technical infrastructure project of the residential area in Phu Xuan Commune, Tho Xuan District began to be implemented by INVESTCORP Land Thanh Hoa Company with items and volumes according to the contract. Some of the works carried out during the month included excavating and removing weathered soil for the road items and constructing the K95 soil foundation.
Construction progress updated in September 2023 – Technical infrastructure project of residential area in Xuan Hoa - Tho Hai commune, Tho Xuan district, Thanh Hoa province

Construction progress updated in September 2023 – Technical infrastructure project of residential area in Xuan Hoa - Tho Hai commune, Tho Xuan district, Thanh Hoa province

In September 2023, for the Technical infrastructure project of the residential area in Xuan Hoa - Tho Hai commune, Tho Xuan district, Thanh Hoa province, INVESTCORP Land Thanh Hoa focused on implementing road construction such as excavation and transportation of weathered soil reached 20%; K95 soil transportation and embankment reached 13% and K98 soil transportation and embankment work reached 16%.
Construction progress updated in September 2023 – Autoliv Vietnam project

Construction progress updated in September 2023 – Autoliv Vietnam project

At the end of September 2023, INVESTCORP basically completed temporary items at the Autoliv Vietnam project including temporary offices, temporary gates, temporary roads, temporary drainage systems, and a number of other temporary items serving construction work.
Construction progress updated in September 2023 – Residential Area Technical Infrastructure Project in Quang Dong commune, Thanh Hoa city

Construction progress updated in September 2023 – Residential Area Technical Infrastructure Project in Quang Dong commune, Thanh Hoa city

In September 2023, for the road category of the Residential Area Technical Infrastructure Project in Quang Dong commune, Thanh Hoa city, INVESTCORP Land Thanh Hoa Company completed 83% of the K95 soil road embankment, 91% of the K98 soil road embankment, 80% of the type I macadam foundation construction and 90% of the type II macadam foundation.
Construction progress updated in August 2023 - TOYO INK COMPOUNDS Vietnam Factory Project Phase 3

Construction progress updated in August 2023 - TOYO INK COMPOUNDS Vietnam Factory Project Phase 3

At the end of August 2023, INVESTCORP 10 basically completed pouring heat-resistant concrete for the roof, painting and removing the scaffolding outside the house; complete indoor wall and ceiling beams for the factory.
Construction progress updated in August 2023 – Residential Area Technical Infrastructure Project in Quang Dong commune, Thanh Hoa city

Construction progress updated in August 2023 – Residential Area Technical Infrastructure Project in Quang Dong commune, Thanh Hoa city

In August 2023, INVESTCORP Land Thanh Hoa constructed the K95 road embankment at 83%; the K98 road embankment construction at 91%; construction of crushed stone foundation grade II at 90%; and construction of crushed stone foundation grade I reached 80%.
Construction progress updated in August 2023 – Typical Residential Area Infrastructure Project in Hoang Hoc Village, Dong Hoang Commune, Dong Son District, Thanh Hoa Province

Construction progress updated in August 2023 – Typical Residential Area Infrastructure Project in Hoang Hoc Village, Dong Hoang Commune, Dong Son District, Thanh Hoa Province

In August 2023, INVESTCORP Land Thanh Hoa focused on constructing finishing work items, including road construction reached 100% of the volume; drainage system construction reached 100%; tiling work reached 100%.
Construction progress updated in August 2023 – Sao Mai Resort Project, Tho Lam Commune – Tho Xuan District – Thanh Hoa Province

Construction progress updated in August 2023 – Sao Mai Resort Project, Tho Lam Commune – Tho Xuan District – Thanh Hoa Province

In August 2023, INVESTCORP 6 continued to construct plastering and tiling for Family Villas. For the reception area, INVESTCORP 6 is implementing tiling and completing exterior items.
Construction progress updated in August 2023 – Technical infrastructure project of residential area in Xuan Hoa - Tho Hai commune, Tho Xuan district, Thanh Hoa province

Construction progress updated in August 2023 – Technical infrastructure project of residential area in Xuan Hoa - Tho Hai commune, Tho Xuan district, Thanh Hoa province

In August 2023, INVESTCORP Land Thanh Hoa mobilized machinery and human resources to carry out the construction of items and volumes according to the contract. Works performed during the month including excavation and transportation of weathered soil; transportation and embankment of K95 soil work.
Construction progress updated in August 2023 - Project of renovating and upgrading rescue road in Truong Xuan commune to left dike of Chu River, Tho Xuan district, Thanh Hoa province

Construction progress updated in August 2023 - Project of renovating and upgrading rescue road in Truong Xuan commune to left dike of Chu River, Tho Xuan district, Thanh Hoa province

In August 2023, INVESTCORP Land Thanh Hoa completed all work items, including lighting items, road surface items, and drainage system. Total construction volume is estimated at 50%.
Construction progress updated in August 2023 - Renovation and upgrading project of provincial road 506B, section from Tho Lap commune to Xuan Tin commune, Tho Xuan district

Construction progress updated in August 2023 - Renovation and upgrading project of provincial road 506B, section from Tho Lap commune to Xuan Tin commune, Tho Xuan district

In August 2023, INVESTCORP Land Thanh Hoa mobilized human resources to accelerate the excavation and transportation of weathered soil, reaching 67% of the volume; the transportation and embankment work of K95 reached 90% of the volume.
Construction progress updated in July 2023 - TOYO INK COMPOUNDS Vietnam Factory Project Phase 3

Construction progress updated in July 2023 - TOYO INK COMPOUNDS Vietnam Factory Project Phase 3

By the end of July 2023, INVESTCORP 10 has completed the structural works of roof beams, attic, and balustrades for the factory. At the same time, the Company is also implementing the plastering of the surrounding walls at 90%, the inside and outside plastering work is about 70%.
Construction progress updated in July 2023 – An additional tender package under item

Construction progress updated in July 2023 – An additional tender package under item "Finish construction and installation of office furniture" of project "Manufacture of hot and cold packs and high-class cardiac electrode pads – Intco Medical”

In July 2023, INVESTCORP 15 completed preliminarily interior installation work and is currently continuing to carry out cleaning and repair work. The 1st, 2nd and 3rd floor areas have been handed over to the Investor and put into use.