Construction progress updated in May 2023 – Key Technology Hanoi Factory Project Phase 2

Construction progress updated in May 2023 – Key Technology Hanoi Factory Project Phase 2

By the end of May 2023, INVESTCORP 9 has completed 85% of the work volume of the whole project, including plastering the main factory at 98%, erecting steel and concreting the main factory floor at 90%; erecting steel and pouring concrete of painting house reached 50%.
Construction progress updated in May 2023 – An additional tender package under item

Construction progress updated in May 2023 – An additional tender package under item

In May 2023, INVESTCORP 15 completed the erection of drywall frames, gypsum ceiling frames, toilet wall tiles, stair paving, and electrical wiring for sockets and lighting systems.
Construction progress updated in May 2023 – An additional tender package of

Construction progress updated in May 2023 – An additional tender package of "Detention basin to store after-treatment water" under "Textile and Garment Factory Project of Ramatex Nam Dinh - Phase 1"

In May 2023, INVESTCORP 15 completed spreading GCL sheets and HDPE sheets, and pouring concrete to block HDPE sheets. Along with that, the pump room was also installed with the door and roof; the cleaning, sanitizing, and defect repair are also carried out in parallel.
Construction progress updated in May 2023 - TOYO INK COMPOUNDS Vietnam Factory Project Phase 3

Construction progress updated in May 2023 - TOYO INK COMPOUNDS Vietnam Factory Project Phase 3

By the end of May 2023, INVESTCORP 10 has completed the construction of 1st floor and 2nd floor columns and 2nd floor beams of the factory. For the warehouse, the Company is implementing steel erection and surrounding wall construction. In the powerhouse area, the Company is implementing plastering and roof structure processing.
Construction progress updated in May 2023 – Road project from Xuan Hung commune connecting with road from Tho Xuan town to Lam Son – Sao Vang urban area, Tho Xuan district

Construction progress updated in May 2023 – Road project from Xuan Hung commune connecting with road from Tho Xuan town to Lam Son – Sao Vang urban area, Tho Xuan district

By the end of May 2023, INVESTCORP Land Thanh Hoa has constructed 100% of asphalt pavement, asphalt concrete spreading with 100% of the volume, and construction of crushed stone for horizontal roads reaches 100%. Total construction output is estimated at 89% of the contract volume.
Construction progress updated in May 2023 – Sao Mai Resort Project, Tho Lam Commune – Tho Xuan District – Thanh Hoa Province

Construction progress updated in May 2023 – Sao Mai Resort Project, Tho Lam Commune – Tho Xuan District – Thanh Hoa Province

At the end of May 2023, INVESTCORP 6 basically completed the items of the Four Seasons Rubby Villa, the Bungalow under the lake, and is finishing the interior furniture. For the reception house, INVESTCORP 6 completed the construction of the structure and completed the plastering.
Construction progress updated in May 2023 – Typical Residential Area Infrastructure Project in Hoang Hoc Village, Dong Hoang Commune, Dong Son District, Thanh Hoa Province

Construction progress updated in May 2023 – Typical Residential Area Infrastructure Project in Hoang Hoc Village, Dong Hoang Commune, Dong Son District, Thanh Hoa Province

In May 2023, INVESTCORP Land Thanh Hoa focused on speeding up the construction progress and completing the road items and the drainage system.
Construction progress updated in May 2023 – Additional tender package for construction of “Rooftop solar power system” under ‘‘Wearing apparel manufacturing factory project of Maple Company in Hai Phong’’

Construction progress updated in May 2023 – Additional tender package for construction of “Rooftop solar power system” under ‘‘Wearing apparel manufacturing factory project of Maple Company in Hai Phong’’

At the end of May 2023, INVESTCORP 10 completed pouring the roof pillars of Factories 1, 2, 3, and 4 and the roofs of Offices 1 and 2. At the same time, the Company is also processing battery racks and has completed the installation of Factories 1 and 2’s panel racks and the construction of control rooms of Factories 1 and 2.
Construction progress updated in May 2023 – Residential Area Technical Infrastructure Project in Quang Dong Commune, Thanh Hoa City, Thanh Hoa Province

Construction progress updated in May 2023 – Residential Area Technical Infrastructure Project in Quang Dong Commune, Thanh Hoa City, Thanh Hoa Province

In May 2023, INVESTCORP Land Thanh Hoa completed 83% of the K95 soil embankment, 91% of the K98 soil embankment, 90% of the grade II crushed stone foundation, and 10% of the grade I one. At the same time, the installation of D400 and D600 drainage systems was also constructed by the Company with 91% of the contract volume.
Construction progress updated in April 2023 – An additional tender package under item

Construction progress updated in April 2023 – An additional tender package under item "Finish construction and installation of office furniture" of project "Manufacture of hot and cold packs and high-class cardiac electrode pads – Intco Medical”

In April 2023, INVESTCORP 15 completed painting the outside beams and columns and handed them over to the construction unit erecting the outside glass wall to continue implementing the following works; the erection of the steel frame reinforcing drywall system has also been completed. 
Construction progress updated in April 2023 – An additional tender package of

Construction progress updated in April 2023 – An additional tender package of "Detention basin to store after-treatment water" under "Textile and Garment Factory Project of Ramatex Nam Dinh- Phase 1"

At the beginning of April 2023, INVESTCORP 15 implemented the construction of the additional tender package under the "Textile and Garment Factory Project of Ramatex Nam Dinh- Phase 1".
Construction progress updated in April 2023 - TOYO INK COMPOUNDS Vietnam Factory Project Phase 3

Construction progress updated in April 2023 - TOYO INK COMPOUNDS Vietnam Factory Project Phase 3

By the end of April 2023, INVESTCORP 10 has completed the construction of the factory foundation beams and floors. At the same time, the Company is implementing steel foundation erection and steel structure processing for warehouses and steel construction for electric houses.By the end of April 2023, INVESTCORP 10 has completed the construction of the factory foundation beams and floors. At the same time, the Company is implementing steel foundation erection and steel structure processing for warehouses and steel construction for electric houses.By the end of April 2023, INVESTCORP 10 has completed the construction of the factory foundation beams and floors. At the same time, the Company is implementing steel foundation erection and steel structure processing for warehouses and steel construction for electric houses.
Construction progress updated in April 2023 – Sao Mai Resort Project, Tho Lam Commune – Tho Xuan District – Thanh Hoa Province

Construction progress updated in April 2023 – Sao Mai Resort Project, Tho Lam Commune – Tho Xuan District – Thanh Hoa Province

In April 2023, INVESTCORP 6 Company completed the construction of structural concrete and plastering at the reception area. At the Family villa area, INVESTCORP 6 started the construction of the foundation and structure.