Construction progress updated in September 2023 – Autoliv Vietnam project
At the end of September 2023, INVESTCORP basically completed temporary items at the Autoliv Vietnam project including temporary offices, temporary gates, temporary roads, temporary drainage systems, and a number of other temporary items serving construction work.
At present, INVESTCORP completes all experimental pile pressing work and is starting to carry out static compression work.
Other news
- Announcement of Holiday schedule for Apr 30 and May 1, 2024
- Autoliv’s Chairman visits and works at the Autoliv Vietnam Factory project – Amata Song Khoai Industrial Park – Quang Yen Town – Quang Ninh Province
- Discussion program to celebrate the 114th anniversary of International Women′s Day March 8
- Groundbreaking ceremony of Jehong Textile Factory Project
- Enjoy spring of the new year Giap Thin 2024
- INVESTCORP Group begins the Spring of the Dragon year 2024
- INVESTCORP Group organizes the Year-End Party 2023 – Happy New Year 2024
- Announcement of Tet Holiday 2024
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED