Construction progreConstruction progress updated in October 2023 – Technical infrastructure project of residential area in Xuan Hoa - Tho Hai commune, Tho Xuan district, Thanh Hoa province

In October 2023, for the traffic category, K95 soil road surface work reached 32% of the volume and K98 soil road surface work reached 42%.

The construction of curbs and drainage ditches reached 14%. Total output is estimated to reach 10% of contract value.

According to the plan for November 2023, INVESTCORP Land Thanh Hoa will focus on implementing the construction of traffic items, speeding up the K98 soil embankment, constructing type 2 macadam foundations for entire routes, and constructing drainage ditches, installing the curbing system to ensure quality and progress in the contract.