Construction progress updated in August 2023 – Typical Residential Area Infrastructure Project in Hoang Hoc Village, Dong Hoang Commune, Dong Son District, Thanh Hoa Province

In August 2023, INVESTCORP Land Thanh Hoa focused on constructing finishing work items, including road construction reached 100% of the volume; drainage system construction reached 100%; tiling work reached 100%.

As planned in September 2023, INVESTCORP Land Thanh Hoa will complete the connection and acceptance of the power supply, water supply, and fire protection systems for the project; at the same time, take acceptance and handover of the project for use.

 