Construction progress updated in August 2023 – Residential Area Technical Infrastructure Project in Quang Dong commune, Thanh Hoa city
In August 2023, INVESTCORP Land Thanh Hoa constructed the K95 road embankment at 83%; the K98 road embankment construction at 91%; construction of crushed stone foundation grade II at 90%; and construction of crushed stone foundation grade I reached 80%.
In addition, the Company also basically completed the installation of D600 and D400 drainage systems. Total volume is estimated at 48%.
As planned in September 2023, INVESTCORP Land Thanh Hoa will focus on completing construction of crushed stone for the roads; completion of pavement embankment, installation of electrical systems, clean water supply systems, fire protection and wastewater drainage systems.
Other news
- Announcement of Holiday schedule for Apr 30 and May 1, 2024
- Autoliv’s Chairman visits and works at the Autoliv Vietnam Factory project – Amata Song Khoai Industrial Park – Quang Yen Town – Quang Ninh Province
- Discussion program to celebrate the 114th anniversary of International Women′s Day March 8
- Groundbreaking ceremony of Jehong Textile Factory Project
- Enjoy spring of the new year Giap Thin 2024
- INVESTCORP Group begins the Spring of the Dragon year 2024
- INVESTCORP Group organizes the Year-End Party 2023 – Happy New Year 2024
- Announcement of Tet Holiday 2024
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED