Construction progress updated in October 2023 - Renovation and upgrading project of provincial road 506B, section from Tho Lap commune to Xuan Tin commune, Tho Xuan district

In October 2023, INVESTCORP Land Thanh Hoa Company mobilized machinery and human resources to carry out the construction of items under the Renovation and upgrading project of provincial road 506B, section from Tho Lap commune to Xuan Tin commune, Tho Xuan district.

Regarding the road surface, INVESTCORP Land Thanh Hoa has constructed 77% of the excavation and transportation of weathered soil. The K95 transportation and earthworks were also completed 91% of the total work volume.

The K98 soil transportation and embankment work reached 15% of the volume. 12% of crossroad intersections and 37% of sewer construction were also completed. Total output is estimated to reach 19% of contract value.

According to the plan for November 2023, INVESTCORP Land Thanh Hoa Company Limited will focus on implementing the construction of the road surface, speeding up the K98 soil embankment all the route, and constructing drainage pipes to ensure quality and progress in the contract.