Construction progress updated in September 2023 - Renovation and upgrading project of provincial road 506B, section from Tho Lap commune to Xuan Tin commune, Tho Xuan district

In September 2023, INVESTCORP Land Thanh Hoa continued to focus on mobilizing machinery and human resources to implement construction items under the Renovation and upgrading project of provincial road 506B, the section from Tho Lap commune to Xuan Tin commune, Tho Xuan district.

For the road surface, INVESTCORP Land Thanh Hoa constructed 77% of the excavation and transportation of weathered soil. The K95 transportation and embankment were also completed 91% of the total work volume. The construction of intersections, crossroads, and drainage system items has also begun.


As planned in October 2023, INVESTCORP Land Thanh Hoa will focus on implementing the construction of the road surface, speeding up excavating weathered soil, filling K95 and K98 soil along the entire route, and constructing sewers.

 