Construction progress of Biel Crystal Vietnam Factory Project in October 2017
Following the signed construction progress, by the end of October 2017, the Contractor INVESTCORP has completed the Biel Crystal Vietnam factory project and handed-over to the Owner to move to the next construction phase.
At present, some additional works are being carried out by the Contractor such as PIT for machines and fire protection… The remaining additional works will be implemented and completed according to requirements of the Owner.
Other news
- Autoliv’s Chairman visits and works at the Autoliv Vietnam Factory project – Amata Song Khoai Industrial Park – Quang Yen Town – Quang Ninh Province
- Announcement of Holiday schedule for Apr 30 and May 1, 2024
- Discussion program to celebrate the 114th anniversary of International Women′s Day March 8
- Groundbreaking ceremony of Jehong Textile Factory Project
- Enjoy spring of the new year Giap Thin 2024
- INVESTCORP Group begins the Spring of the Dragon year 2024
- INVESTCORP Group organizes the Year-End Party 2023 – Happy New Year 2024
- Announcement of Tet Holiday 2024
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED